THE ELEMENT HOTEL
The Element Hotel project aims to convert an existing 12-storey office building to hotel/residential use with approximately 168,037 sq. ft. of indoor space, with additional 2 levels of underground parking.
Site Superintendents: Robert Blades & Travis Ophof
Site Foremen: Justin MacFarlane & Justin Keller
Project Manager: Paul Smolarz
Project Coordinator: Franz Lorenzana
Contract Type: CCDC5B
Project Location: Calgary, AB
Project Worth: $35 Million
Completion Date: June, 2025 (in progress)
GRAND TOURING AUTO
Construction Manager: Tamas Nemeth-Siegl
Contract Type: CCDC5B
Site Superintendent: Justin Keller
Project Location: Calgary, AB
Project Manager: Paul Smolarz & Franz Lorenzana
Completion Date: August, 2024
Project Worth: $4.5 Million
The Grand Touring Auto construction project successfully extended the building’s main entrance, featuring a new window wall system and upgraded exterior cladding finishes. Additionally, the dealership underwent a major renovation of its interior finishes, ensuring that the brand standards of luxury automakers like Rolls Royce and Lamborghini were met to the highest specifications.
HYATT PLACE HOTEL
Project Manager: Tamas Nemeth-Siegl
Contract Type: CCDC5A
Site Superintendent: Robert Blades
Project Location: Calgary, AB
Site Foreman: Justin MacFarlane
Completion Date: November, 2018
Project Worth: $19.5 Million
Located close to YYC International Airport, ARCHICON led the construction of a brand new five-storey Hyatt Place Hotel that houses 127 guest rooms with a fitness center, pool, restaurant, and meeting facilities. It involves extensive structural concrete work for elevator shafts, a pool deck, and floor slabs. ARCHICON was responsible for overseeing the design and construction of this project and delivered under a Construction Management contract to ensure costs were monitored and stayed within budget. |
WESTLEY HOTEL
Project Manager: Tamas Nemeth-Siegl
Contract Type: CCDC5A
Project Coordinator: Franz Lorenzana
Project Location: Calgary, AB
Site Superintendent: Justin Keller
Completion Date: June, 2021
Project Worth: $16.7 Million
Located in Downtown Calgary, this five-storey boutique hotel project utilizes an old office building and converted it into 104 European-style rooms complete with a restaurant & lounge/bar area, private dining rooms, meetings, and a fitness room. |
HOLIDAY INN EXPRESS HOTEL & SUITES
Project Manager: Tamas Nemeth-Siegl
Contract Type: CCDC5A
Project Coordinator: Franz Lorenzana
Site Superintendent: Robert Blades
Site Foreman: Justin MacFarlane
Project Location: Calgary, AB
Project Worth: $15.2 Million
Completion Date: October, 2020
This new six-storey hotel is located in the Airport District in Calgary, Alberta and offers 100 family-oriented rooms with features such as meeting rooms, fitness rooms, breakfast areas, and a swimming pool with waterslides.
WESTVIEW HEIGHTS
Construction Manager: Tamas Nemeth-Siegl
Project Manager: Paul Smolarz & Franz Lorenzana
Site Superintendent: Justin Keller
Project Location: Downtown, Calgary, AB
Contract Type: CCDC2
Completion Date: August, 2023
Project Worth: $22.4 Million
Located in downtown Calgary, the project focused on converting 4 commercial floors into 44 new rental suites. During construction, the project evolved into renovations of 6 additional floors and an upgrade to the Mechanical, Electrical, and Fire Safety systems for building. |
THE KENTEN
“Premium Living Like Nothing Else” – The Kenten, 2023, https://www.thekenten.ca
Archicon has been commissioned by the developer, Sable Group of Companies, to proceed with the pre-construction services for The Kenten project. Located on the iconic corner of 10th and Memorial Street, this project aims to provide Calgary with “Premium Living Like Nothing Else”.